NTPC Green Energy Adds 81.34 MW Solar Capacity in Rajasthan, Group Capacity Rises to 11,058.57 MW

NTPC Green Energy Limited has announced the commercial operation of the first part of the capacity of its Kalasar Solar Energy Project in Bikaner, Rajasthan, marking another addition to its renewable energy portfolio.
According to the company’s exchange filing dated September 26, 2026, an 81.34 MW portion of the Kalasar Solar Energy Project was declared commercially operational with effect from 00:00 hours on September 26, 2026.
The project is part of the 650 MW solar component under the 500 MW REMCL RTC Project of NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy.
81.34 MW Solar Capacity Becomes Operational
The newly commissioned 81.34 MW capacity is located in Bikaner, Rajasthan, one of India’s major renewable energy development regions.
NTPC Green Energy said the capacity forms part of the solar component associated with the 500 MW REMCL RTC Project. The commercial operation declaration means this portion of the project has entered commercial operations.
The company has been expanding its renewable energy portfolio across solar and other clean-energy projects, and the latest commissioning adds to its operational capacity.
NTPC Green Energy Group Capacity Crosses 11,000 MW
Following the commissioning of the 81.34 MW capacity, the commercial capacity of the NTPC Green Energy Limited group stands at 10,977.23 MW, according to the company’s filing.
The company’s disclosure further states that the total installed capacity of the NTPC Green Energy group has increased to 11,058.57 MW.
This latest capacity addition therefore takes the group’s installed renewable-energy capacity further above the 11 GW mark.
Project Details at a Glance
- Company: NTPC Green Energy Limited
- Project: Kalasar Solar Energy Project
- Location: Bikaner, Rajasthan
- Capacity declared commercial: 81.34 MW
- Solar component: 650 MW
- Associated project: 500 MW REMCL RTC Project
- Subsidiary: NTPC Renewable Energy Limited
- Commercial operation date: September 26, 2026
- Group commercial capacity: 10,977.23 MW
- Group installed capacity: 11,058.57 MW
Why This NTPC Green Energy Update Matters
The commissioning is an operational milestone for NTPC Green Energy because it adds generating capacity to the company’s renewable-energy portfolio.
The announcement also provides investors with an update on the execution of the company’s renewable-energy projects. However, the exchange filing does not provide details of the immediate revenue or profit contribution from the 81.34 MW capacity.
The financial impact will depend on factors such as generation, project utilisation, applicable power-sale arrangements and other operating parameters.
What Investors Should Watch
Investors tracking NTPC Green Energy may continue to monitor:
- Further commissioning of the remaining capacity under ongoing solar projects
- Growth in the company’s operational renewable-energy portfolio
- Execution of large solar, wind and hybrid renewable projects
- Capacity additions and project timelines
- Power generation and utilisation levels
- Future earnings contribution from newly commissioned assets
Bottom Line
NTPC Green Energy has commissioned 81.34 MW of the Kalasar Solar Energy Project in Bikaner, Rajasthan, effective September 26, 2026. The addition takes the NTPC Green Energy group’s installed capacity to 11,058.57 MW, according to the company’s exchange filing.
The development represents another step in the company’s renewable-energy capacity expansion, while the actual financial contribution from the newly commissioned capacity will become clearer through subsequent operational and financial disclosures.
Source: NTPC Green Energy Limited exchange filing dated September 26, 2026.
Disclaimer: This article is for informational purposes only and should not be considered investment advice. Investors should conduct their own research and evaluate the company’s financials, project execution, valuation, and risks before making any investment decision.