Wednesday, 29 July 2026

Indian corporate news, decoded into deal flow

NSE LIVE
NIFTY 50 INDIA VIX
as of
MARKETS
DEAL FLOW
Eris Lifesciences Q1 FY27 PAT Rises… ▲ Results Details Meghmani Organics Highlights Global Expansion and… ▲ Results Details Teamlease Services Limited Reports Q1FY27 PAT… ▲ Results Details Aequs Reports 55% Revenue Growth in… ▲ Results Details Cupid Limited Invests Additional USD 5… ▲ Capex & Future Plans Dabur India Reports 15% Growth in… ▲ Results Details Unihealth Hospitals Achieves Regional First with… ▲ Market News / Economy
Home / Order Book / Bajel Projects Secures ₹765kV Transmission Line EPC Contract from PowerGrid
OB · Order Book

Bajel Projects Secures ₹765kV Transmission Line EPC Contract from PowerGrid

Bajel Projects Secures ₹765kV Transmission Line EPC Contract from PowerGrid

Bajel Projects Limited has been awarded a significant order for the supply of goods and services. Below are the key highlights of the contract:

Awarding Entity

The order has been issued by PowerGrid Corporation of India Limited (POWERGRID) through its project-specific Special Purpose Vehicle (SPV), Rajasthan IV 4A Power Transmission Limited.

Nature of the Order

The contract is for an EPC (Engineering, Procurement, and Construction) project involving the construction of a 765kV transmission line. It encompasses the supply of goods and services necessary for the project.

Project Details

  • Package Name: Transmission Line Package TL03
  • Scope: Construction of the Dausa – Ghiror 765 kV D/c Line (Part-III)
  • Purpose: Part of the transmission system for evacuating power from Rajasthan REZ Ph-IV (Part-4: 3.5 GW): Part A
  • Length: Approximately 120 km of a 765kV new transmission line

Timeline

The project is expected to be completed within 23 months from the issuance of the Notice of Award.

Domestic Contract

This is a domestic order awarded by an Indian entity, underscoring Bajel Projects Limited’s strong presence in the local market.

This contract highlights Bajel Projects Limited’s capability to execute large-scale transmission line projects, further strengthening its position in the Indian EPC sector. The timely execution of this project will contribute significantly to the infrastructure for renewable energy evacuation from Rajasthan’s REZ Ph-IV.